Billings, Montana Water Treatment Plant Expansion
Demo existing Filter Building and construct a new Filter Building with 8 new Filters.
Install 1000’ of Concrete Encased Underground Ductbank
Installation of 600 KW Generator with ATS.
New fiber optic network.
Installation of 11 new PLCs, associated instruments, HMI Programming, Operator Workstations, and UPS System. |
|
Billings, Montana Waste Water Treatment Plant
Construction of New Headworks Facility
Removal of PCB contaminated HV Transformer
Installation of 1000’ of Concrete Encased Underground Ductbank
Extension of existing fiber optic network.
Class 1 Division 1 Electrical Installations
Instrumentation work including installation of new PLCs, Flow Meters, Level Transmitters, Pressure Indicators, Device Net Equipment, HMI Programming and Operator Workstations. |
|
Gillette, WY Waste Water Treatment Plant
New Aeration Basins, Dewatering Unit, and Chlorine Unit.
Remodel of Grit Unit, Blower Unit, Digester Unit, and Influent Unit.
Installation of 6000' of concrete encased underground ductbank.
Class 1, Division 1 installations.
New fiber optic network.
Installation of 8 new PLCs, associated instrumentation, HMI programming, and operator work stations. |